project

Little Creatures Brewery

Conversion of a 1920’s red brick woolen mill into a $60m state of the art brewery using German technology. The second stage included a 400-capacity hospitality area. The design retained and re-used the historical building elements wherever possible.

Edison Consultants provided mechanical, electrical & fire services for the Brewery project, as well as the Hospitality project.

Co-generation combined heat and power (CHP) system using gas-fired generators to produce electricity and the waste heat for the brewing process.

  • Client:   Lion Nathan / Little Creatures
  • Project Manager: TGM Group
  • Builder:   Kane Constructions


Geelong, VIC