project

Murray Goulburn, Smithton

This $80 million plant has a processing capacity of 300 million litres or 40,000 tonnes of dairy products per year.

The project involved a new 35m tall evaporator, spray dryer and packaging building with 3 hygiene areas. The building includes a red-line change area, lactose room, control room, MCC, boiler room and transformer yard.

The second stage included a Bulk Fill building with closely monitored temperature & humidity control, filtration and zone pressurisation to maintain hygiene standards.

Edison Consultants worked collaboratively with the principal consultant 4site Engineering

Client: Murray Goulburn

 

 


Smithton, TAS